Irrigation Project - Phase 1
Work Commences Monday 20th October
During the 6-week project we will be installing new irrigation to all 18 tee complexes, as well as the greens and approaches on holes 2, 3, 4, 13, 14 and 18 and a new system for the putting green.

The works will include installation of approximately 5,500m of lateral pipework as well as 200 tee sprinklers, 40 greens & approach sprinklers and all the control valves and chambers.

The project also includes the supply and installation of new Lowara variable speed pumping station that will produce 55,000 litres of water per hour for distribution across the course.

During the project there will be a high level of machinery movement and cross over. Whilst the contractors will always endeavour to be as courteous as possible with machinery and installation works there will be occurrences of cross over with both golfers and visitors to the course, so we pre-apologise for any inconvenience caused during our works.

Whilst individual greens and tees are being worked on play will be moved to temporary forward tees and temporary greens for the duration of works specific to the hole.

Weekly update newsletters will be produced to keep all members and guests up to date on the project progress, and all information will be stored in the Irrigation documents folder on the Members' Hub.